How will the purpose of this strip of land affect the parcels north of subject area and what are the plans, if any, for these areas?

    The lands north of the Study Area have been allocated (through ROPA 49) to accommodate employment growth to 2051. They would need to be studied further in the future and a secondary plan  developed at that time.

    Can the houses be rezoned to commercial?

    Existing residential uses are proposed to be identified as legally permitted uses within the Employment designation. Policies, permitting additional home occupation and/or office uses within the existing, long-standing properties can be added into the Secondary Plan. Policies required for appropriate mitigation measures / buffers between existing residential uses and new employment uses will be included in the Secondary Plan, too. 

    Commercial uses are being proposed at the corner of Winston Churchill Boulevard and Steeles. 

    More information about the proposed designations in the preferred land use plan can be found in the Land Use Options Report.

    No Trees?

    The preservation and planting of trees is a priority in the Urban Design Guidelines and existing trees will be protected, where possible. The Subwatershed Study also established the Natural Heritage System that calls for buffers, additional green areas around existing and new features, providing opportunities to add additional vegetation, including trees.

    Water collection at buildings to water trees?

    The project team will look into this further to determine whether or not water collection can be included in the Urban Design Guidelines.

    Where employment lands come close to residential homes, has there been any consideration to light pollution? How can lighting pollution be mitigated when near homes?

    Light pollution is considered under the Urban Design Guidelines and there are mitigation measures in place to reduce the impact of lighting adjacent to residential properties.   

    Some options include locating areas requiring lighting (parking lots and building entrances) away from residential areas and providing guidelines for promoting shades that down cast light automatically, making it bird and people friendly.

    The site plan process would also require an applicant to comply with dark sky compliance standards and provide photometric plans to ensure there is zero light spillage beyond the lot lines.

    What consideration has been given to the salt treatment in winter (approximately 5 months of the year) applied to roads, parking lots, sidewalks regarding its impact on the watershed and flora and fauna?

    There are a variety of ways salt impacts can be managed. Halton Region and the Town have a Salt Management Plan that requires the Region and the Municipality to report salt usage. There are also alternative materials to salt that can be used. 

    In terms of recommendations for salt use mitigation, the buffers around the system intercept salt that may be used, effectively taking it out of the run-off or capturing it before it reaches the vegetative system or feature. Evidence shows certain LIDs can reduce the reliance of salt.

    Regarding the site-specific application at 8079 Eighth Line, are there any envisioned concerns or comments?

    More information about the development application for 8079 Eighth can be found here.

    Given outdoor storage needs and current unpermitted outdoor storage use in the area, why are we not considering outdoor storage as a permitted use?

    The Premier Gateway Area is planned to accommodate highly generating employment uses. Outdoor Storage will not be permitted.

    I'm the Rector of St. Stephen's Anglican Church & Cemetery on the south side of Steeles at the Ninth Line N intersection. Will the over 250 cemetery plots and historic church building be protected?

    The cemetery is protected under the Cemeteries Act. And, as part of the development application, any development adjacent to a listed or designated heritage property in the Premier Gateway area will be subject to a heritage impact assessment.

    What do you anticipate will be the impact of the Federal Ministry of the Environment decision to have a full Assessment of the 413 project?

    The Highway 413 team is part of the Technical Advisory Committee (TAC) for Premier Gateway Phase 2B and we anticipate that any impacts to the environmental assessment will be communicated to the committee. The Town is following the Highway 413 project closely and staying engaged with the province to ensure that we have the most up-to-date information as the Premier Gateway Phase 2B Secondary Plan is being finalized.

    When will all this be completed by (i.e., developing these lands)?

    The Secondary Plan will be completed this year; however, the timeline for the area to be fully developed depends on the development application process and the future construction timelines associated with each development.

    I believe that the special plan policy should allow high density apartment buildings in that specific area, so people are able to work and live in close proximity to each other. Why is this not allowed?

    As a designated employment area there are noise, air quality and compatibility concerns about introducing new residential uses. The province further emphasizes maintaining employment areas for its designated use, and therefore new residential uses will not be permitted.

    Can the extra road you are putting in not end on 8th line instead of Steeles on the west side?

    The team considered the option of extending the road to Eighth Line; however, due to the potential environmental impacts of crossing the Sixteen Mile Creek, it was determined that there were minimum benefits for the transportation network and that the road should end east of the Sixteen Mile Creek.

    Will the Town of Halton Hills provide planned transportation and a servicing network for the surrounding area?

    There is currently an existing operating transit route from Milton Transit via a partnership between the Town of Halton Hills and the Town of Milton. The local bus route generally operates in an east-west direction between Lisgar GO Station in Mississauga and the Milton GO Station, with several stops within Halton Hills. Currently, the service is operated weekdays (6 a.m. -10 p.m.) and Saturdays (7:30 a.m. -7:30 p.m.) with no Sunday service.

    As development progresses on Steeles Ave, the service will be reviewed and the need for expanded service considered. Including future developments north and south of Steeles, will be considered when the Town’s Transit Service Strategy is reviewed.   

    Does the Region intend to expropriate any land for public right-of-way once the secondary plan is approved?

    Any potential land needs for road expansions or to accommodate servicing infrastructure will be determined through future studies.

    One of our projects is located at 8223 Eighth Line, north of Eighth Line and Steeles Avenue, the property abuts the Secondary Plan Boundary. Are there additional land uses planned for the area?

    The lands north of the Study Area have been allocated through ROPA 49 to accommodate employment growth to 2051. Those lands would need to be studied further in the future; a secondary plan will be developed specifically for those lands.

    What's the width of Phase B from Steeles?

    The Phase 2B area is approximately 257 hectares and is located north of Steeles Avenue, between Eighth Line and Winston Churchill Boulevard, in Halton Hills. The distance from Steeles to the Study Area boundary is approximately 600 m.

    What will happen to the lands that come in the Highway 413?

    Any lands not needed for the highway in the future will be available for the development of prestige employment uses.

    Could dewatering activities during construction affect water wells at existing residents?

    As part of the subwatershed study recommendations whenever construction is being undertaken, developers are required to obtain a permit/guidance from the Ministry of the Environment, Conservation and Parks, and follow the requirements and guidelines to ensure there are no impacts to wells.

    It was mentioned that there are no plans for the ‘strip of lands’ north of the 2B lands. Please clarify, as these lands have been brought into the Regional Urban Boundary under ROPA 49 and SP at the Town level may commence between 2026-2028.

    The lands north of the Study Area have been allocated through ROPA 49 to accommodate employment growth to 2051. The area will need to be further studied in the future and a secondary plan will be developed.

    Since Steeles was expanded, we get a lot of water in our front yard. With the new expansion can we expect it to make it worse

    Steeles is a Regional Road. Please contact the Region of Halton directly at 905-825-6000 or 1-866-442-5866 for further information.

    Are there any limitations on the height of buildings in this area? Maximizing land use typically recommends maximizing vertical developments. If there are limitations, what are they?

    The intent is to keep the heights consistent with those permitted in the Premier Gateway Phase 1B Secondary Plan. The maximum height of all buildings or structures within the Prestige Industrial Area will not exceed 6 storeys.

    Is the team tracking/consulting with the City of Brampton team who is leading the Bram West Secondary Plan Review? The BramWest Secondary Plan Review: Land Use Concept Presentation is scheduled for tomorrow evening.

    The City of Brampton Team is in the initiation stage of the project. The Town has been engaging with them and will continue to provide access to the technical work completed for the Premier Gateway Phase 2B so that it can be considered as part of their future technical work for the Bram West Secondary Plan Review.

    Is there any possibility for low-density stack houses on Tenth Line North close to Steeles?

    Existing residential uses are proposed to be identified as legally permitted uses within the Employment designation. However, new residential uses will not be permitted.

    Is 10th line intended to eventually go further south over the 401 and 407? Would this not take traffic away from 9th and Winston?

    Currently there are no plans to extend Tenth Line over Highways 401 & 407.

    Will the town consider straightening out Winston Churchill so that it doesn’t utilize Adamson Street and go straight to Winston Churchill north?

    Winston Churchill Boulevard is outside of the jurisdiction of the Town of Halton Hills, and any design/construction along this road falls within a boundary agreement betwen Peel Region & Halton Region.